Thursday, September 02, 2010 |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
This is an office consolidation and not an
official version of this Act or Regulation. While care has been taken in assembling this
document, it is not warranted to be true and accurate. Official copies of all Provincial
Acts and Regulations are available from
Island
Information Service. All Prince Edward Island
Statutes and Regulations are available on-line (in PDF format) at the
Office of the Legislative Counsel.
- Updated to: January 11, 2006 -
(Includes
Amendments Approved on December 20, 2005) CHAPTER
R-12.1 RENEWABLE
ENERGY ACT MINIMUM
PURCHASE PRICE REGULATIONS Pursuant to section 18 of the
Renewable Energy Act
R.S.P.E.I. 1988, Cap. R-12.1, Council made the following regulations: Definitions Act (a) “Act” means the Renewable Energy Act R.S.P.E.I.
1988, Cap. R-12.1; Consumer Price Index or CPI (b) “Consumer Price Index” or “CPI” means the All-Items
Consumer Price Index for the province as reported annually by Statistics
Canada; interconnection agreement (c) “interconnection agreement” means an interconnection
agreement made for the purchase of electric energy by a public utility from
a renewable energy generator; minimum purchase price (d) “minimum purchase price” or “mpp” means the minimum
purchase price at which a public utility is required to purchase electric
energy from a renewable energy generator as established under subsection
2(1); (e) “operating cost” means $0.02 per kilowatt hour. Application (a) to a renewable energy generator referred to in section 8
of the Act; and (b) to an interconnection agreement made after the date
these regulations come into force. Minimum purchase price 2. (1) Subject to section 3, the minimum purchase price
established for the purchase of electric energy by a public utility from a
renewable energy generator under an interconnection agreement is $0.0775 per
kilowatt-hour. Application of tariff (2) The minimum purchase price established under subsection
(1) that is in effect when an interconnection agreement is entered into
continues to apply in respect of the purchase of electricity under the
interconnection agreement, despite any amendment of subsection (1), during
the greater of the following periods: (a) the term of the interconnection agreement; or (b) a period of 20 years. Exception (3) Subsection (1) does not apply to a renewable energy
generator that produces electric energy using wind power if, on the date of
signing of an interconnection agreement, the public utility
has achieved the minimum energy requirements of subsection 3(1) of the Act. Adjustment, wind energy project 3. The minimum purchase price established under
subsection (1) shall be adjusted on April 1, 2008 and April 1 thereafter by
using the following formula: A + (B X C) where A = mpp B = CPI C = operating cost 4. These regulations come into force on December 31,
2005. _______ |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||