Click here for a PDF version of this Order.

Docket P-6-1A
Order No. PW09-011

IN THE MATTER of an application by Irving Energy Distribution and Marketing for an increase of 4.5 cents per litre in its propane pricing schedule.

BEFORE THE COMMISSION

On Friday, the 27th day of February, 2009.

Maurice Rodgerson, Chair
John Broderick, Commissioner
Chester MacNeill, Commissioner


Order


UPON receiving the application of Irving Energy Distribution and Marketing ("Irving") on February 26, 2009 for an increase of 4.5 cents per litre in all prices in its propane pricing schedule based on increased costs;

AND UPON it appearing to the Commission that the prices resulting from an increase of 4.5 cents per litre in Irving's propane pricing schedule are just and reasonable;

NOW THEREFORE, pursuant to the Island Regulatory and Appeals Commission Act and the Petroleum Products Act,

IT IS ORDERED THAT

1.  the maximum propane prices charged by Irving Energy Distribution and Marketing, effective 12:01 a.m. on Sunday, March 1, 2009, be in accordance with Appendix "A" to this Order, and shall remain in effect until otherwise ordered by the Commission; and

2.  the prices approved herein shall appear on all invoices covering sales or deliveries of propane.

DATED at Charlottetown, Prince Edward Island, this 27th day of February, 2009.

BY THE COMMISSION:

Maurice Rodgerson, Chair

John Broderick, Commissioner

Chester MacNeill, Commissioner


Notice:

Section 58 of the Petroleum Products Act reads as follows:

58.  Where any person has the status of a party or is an intervenor in any hearing before the Commission, he is entitled

(a)  to appeal the decision of the Commission to the Appeal Division; and
(b)  to participate as a party in the hearing of an appeal.

and an appeal shall be on a question of law or jurisdiction only and be governed by section 13 of the Island Regulatory and Appeals Commission Act.

Sections 13.1 (1) and (2) of the Island Regulatory and Appeals Commission Act provide as follows:

13.(1)  An appeal lies from a decision or order of the Commission to the Appeal Division of the Supreme Court upon a question of law or jurisdiction.

(2)  The appeal shall be made by filing a notice of appeal in the Supreme Court within twenty days after the decision or order appealed from and the Civil Procedure Rules respecting appeals apply with the necessary changes.


APPENDIX "A"

IRVING ENERGY DISTRIBUTION AND MARKETING

MAXIMUM PRICES EFFECTIVE MARCH 1, 2009

PRINCE EDWARD ISLAND
 

                                 CATEGORY

CENTS PER LITRE
   

Carburation and Portable Cylinders

81.7
 

Bulk Propane Delivery - Maximum Price

77.6

Dispensing Units

71.6
 

 

 

Carburation Cylinders Handling Fee

33 lb. portable cylinder $3.00 per cylinder
 
Yearly Rental on Cylinders and Tanks
100 lb. portable cylinder

$ 36.00

200 lb. fixed cylinder $ 30.00 per installation
420 lb. fixed cylinder $ 69.00 per installation
334 gallon fixed tank $ 60.00 per installation
500 gallon fixed tank $110.00 per installation
1,000 gallon fixed tank $180.00 per installation
1,750 gallon fixed tank $250.00 per installation
2,000 gallon fixed tank $250.00 per installation

 

Service Rates - Installation Charges
     All installations will be charged on the basis of time and materials used.
     Time will be figured on the inclusion of travel time and shop time where applicable.