IN THE MATTER of an application by Superior Plus Inc. (dba Superior Propane) for a decrease of 4.6 cents per litre in its propane pricing schedule.

BEFORE THE COMMISSION

On Friday, the 29th day of August, 2008.

Maurice Rodgerson, Chair
Brian McKenna, Vice-Chair
John Broderick, Commissioner
Chester MacNeill, Commissioner


Order


UPON receiving the application of Superior Plus Inc. ("Superior") on August 26, 2008 for a decrease of 4.6 cents per litre (cpl) in all prices in its propane pricing schedule based on decreased costs.

AND UPON it appearing to the Commission that the prices resulting from a decrease of 4.6 cpl in Superior's propane pricing schedule are just and reasonable;

NOW THEREFORE, pursuant to the Island Regulatory and Appeals Commission Act and Petroleum Products Act,

IT IS ORDERED THAT

1.  the maximum propane prices charged by Superior Plus Inc. effective 12:01 a.m. on Monday, September 1, 2008, be in accordance with Appendix "A" to this Order, and shall remain in effect until otherwise ordered by the Commission; and

2.  the prices approved herein shall appear on all invoices covering sales or deliveries of propane.

DATED at Charlottetown, Prince Edward Island, this 29th day of August, 2008.

BY THE COMMISSION:

Maurice Rodgerson, Chair

Brian McKenna, Vice-Chair

John Broderick, Commissioner

Chester MacNeill, Commissioner


Notice:

Section 58 of the Petroleum Products Act reads as follows:

58.  Where any person has the status of a party or is an intervenor in any hearing before the Commission, he is entitled

(a)  to appeal the decision of the Commission to the Appeal Division; and
(b)  to participate as a party in the hearing of an appeal.

and an appeal shall be on a question of law or jurisdiction only and be governed by section 13 of the Island Regulatory and Appeals Commission Act.

Sections 13.1 (1) and (2) of the Island Regulatory and Appeals Commission Act provide as follows:

13.(1)  An appeal lies from a decision or order of the Commission to the Appeal Division of the Supreme Court upon a question of law or jurisdiction.

(2)  The appeal shall be made by filing a notice of appeal in the Supreme Court within twenty days after the decision or order appealed from and the Civil Procedure Rules respecting appeals apply with the necessary changes.


APPENDIX "A"

SUPERIOR PLUS INC.

MAXIMUM PRICES EFFECTIVE SEPTEMBER 1, 2008

PRINCE EDWARD ISLAND REGION

               CATEGORY

CENTS PER LITRE
   
Bulk Propane Delivery - Maximum Price

87.6

   
Dispensing Units

79.7

   

   

 
RENTAL CHARGES FOR CYLINDERS AND TANKS

33 Lb. Cylinders

$3.60/Month

100 Lb. Cylinders

$3.60/Month

Residential Installations

$69.00/Installation/Year

Commercial Installations

$110.00/Installation/Year